Apollo 7 Quickstart Flightplan

From Project Apollo - NASSP
Jump to navigation Jump to search

Below is the historical timeframe of events followed on Apollo 7.

MET PROCEDURE NOTES
-003:00:00 LAUNCH - PRE-LAUNCH
+000:00:00 LAUNCH - LAUNCH
+000:08:30 LAUNCH - INSERTION
+000:30:00 SYSTEMS - SYSTEMS CHECK Column 1
+001:00:00 SEPARATION
+014:00:00 8 HOUR REST PERIOD
+022:00:00 SYSTEMS - SYSTEMS CHECK Column 2
+025:25:00 RENDEZVOUS
+028:10:00 SYSTEMS - INITIATE BATTERY CHARGING Battery A
+031:00:00 SYSTEMS - TERMINATE BATTERY CHARGING Battery A
+045:00:00 SYSTEMS - SYSTEMS CHECK Column 3
+046:00:00 8 HOUR REST PERIOD
+054:30:00 SYSTEMS - G&N POWER DOWN
+055:00:00 SYSTEMS - FUEL CELL H2 PURGE
+058:00:00 SYSTEMS - FUEL CELL O2 PURGE
+061:00:00 8 HOUR REST PERIOD
+069:00:00 SYSTEMS - SYSTEMS CHECK Column 4
+069:30:00 SYSTEMS - G&N POWER UP
+070:00:00 SYSTEMS - FUEL CELL O2 PURGE
+075:10:00 MANEUVER - SPS BURN 3rd SPS Burn - MET: +075:48:00, Ap: 295.7km, Pe:165 km
+076:40:00 SYSTEMS - G&N POWER DOWN
+078:00:00 SYSTEMS - INITIATE BATTERY CHARGING Battery B
+081:00:00 SYSTEMS - TERMINATE BATTERY CHARGING Battery B
+088:00:00 SYSTEMS - SYSTEMS CHECK Column 5
+089:00:00 SYSTEMS - G&N POWER UP
+090:00:00 8 HOUR REST PERIOD
+099:15:00 SYSTEMS - G&N POWER DOWN
+106:30:00 SYSTEMS - FUEL CELL O2 PURGE
+107:00:00 8 HOUR REST PERIOD
+115:00:00 SYSTEMS - SYSTEMS CHECK Column 6
+117:20:00 SYSTEMS - G&N POWER UP
+118:00:00 SYSTEMS - FUEL CELL O2 PURGE
+120:10:00 MANEUVER - SPS BURN 4th SPS Burn - MET: +120:43:00, Ap: 290.2 km, Pe: 165.0 km
+124:20:00 SYSTEMS - G&N POWER DOWN
+129:00:00 SYSTEMS - FUEL CELL O2 PURGE
+130:00:00 8 HOUR REST PERIOD
+138:00:00 SYSTEMS - SYSTEMS CHECK Column 7
+139:00:00 SYSTEMS - G&N POWER UP
+145:00:00 SYSTEMS - FUEL CELL O2 PURGE
+148:00:00 SYSTEMS - G&N POWER DOWN
+150:00:00 SYSTEMS - FUEL CELL H2 PURGE
+151:00:00 8 HOUR REST PERIOD
+159:00:00 SYSTEMS - SYSTEMS CHECK Column 8
+160:20:00 SYSTEMS - FUEL CELL O2 PURGE
+160:40:00 SYSTEMS - G&N POWER UP
+164:00:00 MANEUVER - SPS BURN 5th SPS Burn - MET: +165:00:00, Ap: 452.2 km, Pe: 165.0 km
+167:00:00 MANEUVER - INITIATE PTC
+168:00:00 MANEUVER - TERMINATE PTC
+170:00:00 SYSTEMS - G&N POWER DOWN
+171:30:00 SYSTEMS - FUEL CELL O2 PURGE
+173:00:00 8 HOUR REST PERIOD
+181:00:00 SYSTEMS - SYSTEMS CHECK Column 9
+183:00:00 SYSTEMS - FUEL CELL O2 PURGE
+187:20:00 SYSTEMS - INVERTER CHANGEOVER Inverter 3 to MNA/AC1, Inverter 1 off
+191:30:00 SYSTEMS - G&N POWER UP Bypass P51/P52 alignment
+194:45:00 SYSTEMS - G&N POWER DOWN
+195:00:00 SYSTEMS - FUEL CELL O2 PURGE
+196:00:00 8 HOUR REST PERIOD
+204:00:00 SYSTEMS - SYSTEMS CHECK Column 10
+205:00:00 SYSTEMS - G&N POWER UP
+207:30:00 SYSTEMS - FUEL CELL O2 PURGE
+209:10:00 MANEUVER - SPS BURN 6th SPS Burn - MET: +210:08:00, Ap: 434.5 km, Pe: 163.7 km
+219:00:00 SYSTEMS - G&N POWER DOWN
+219:20:00 SYSTEMS - FUEL CELL O2 PURGE
+220:00:00 8 HOUR REST PERIOD
+228:00:00 SYSTEMS - SYSTEMS CHECK Column 11
+233:20:00 SYSTEMS - G&N POWER UP
+237:00:00 SYSTEMS - FUEL CELL O2 PURGE
+238:10:00 MANEUVER - 7th SPS BURN 7th SPS Burn - MET: +239:06:12, Ap: 417.2 km, Pe: 163.3 km
+240:40:00 SYSTEMS - INITIATE BATTERY CHARGING Battery B
+241:00:00 SYSTEMS - G&N POWER DOWN
+243:40:00 SYSTEMS - TERMINATE BATTERY CHARGING Battery B
+244:00:00 SYSTEMS - FUEL CELL H2 PURGE
+245:00:00 8 HOUR REST PERIOD
+253:00:00 SYSTEMS - SYSTEMS CHECK Column 12
+254:20:00 SYSTEMS - FUEL CELL O2 PURGE
+254:40:00 SYSTEMS - G&N POWER UP
+258:00:00 DEORBIT 8th SPS Burn